Project Description:
CHELMSFORD- LOWELL- LAWRENCE- BRIDGE PRESERVATION ALONG I-495
Project will include repairs to five bridges along the I-495 corridor in District 4.
Location:
  • Town of Chelmsford
  • City of Lawrence
  • City of Lowell
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2023
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $8,194,305.70
    Estimated Total Federal Participating Construction Cost: $8,474,275.05
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the STATEWIDE.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 07/22/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: CHELMSFORD
    LAWRENCE
    LOWELL
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • increased to $8,474,275 via STIP action 12.,
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $6,779,420.00
    State Cost: $1,694,855.00
    Total Cost: $8,474,275.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/23/2021
    Project Initiation Form PIF Entered 02/23/2021
    Project Initiation Form PRC Submitted 02/23/2021
    Project Review Committee PRC Approved 03/02/2021
    Project Status Advertised 07/22/2023
    Project Management
    100% Design 100% Package Received 08/26/2022
    100% Design 100% Package Comments to DE 11/04/2022
    100% Design 100% Package Received - Resub 1 12/02/2022
    Final Design PS&E Received 04/10/2023
    Final Design PS&E Received - Resub 1 05/25/2023
    Final Design PS&E Received - Resub 2 06/26/2023