Project Description:
BRAINTREE- WEYMOUTH- RESURFACING AND RELATED WORK ON ROUTE 3
The Southern limit of the project begins at the Hingham-Weymouth town line and proceeds North for approximately 5.9 miles. The work to be carried out during the duration of this contract shall consist of 1” depth pavement fine milling, crack sealing of the milled surface, and resurfacing with a 0.75” Ultra-Thin Bonded Overlay Polymer for the Route 3 mainline, from MM 36.35 to MM 42.25, as well as crack sealing of interchange ramps. Guardrail adjustment will be done along the entire length of the project to bring current W-Beam guardrail up to NCHRP-350 compliancy as well as removing and replacing any thrie beam panels that aren’t up to compliance. Work also includes reinstallation of pavement markings/markers. Cleaning, repairing, and adjusting existing drainage structures will be included in resurfacing work done as deemed necessary by the resident engineer. All work shall be performed within, and accessed by, existing State, City, or Town roadway layouts. No rights to enter on, or occupy, private property have been acquired for this project.
Location:
  • Town of Braintree
  • Town of Weymouth
  • Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Eric I Nova
    Estimated Total Contract Cost: $12,524,291.30
    Estimated Total Federal Participating Construction Cost: $12,713,777.50
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 75% Package Received (as of 05/14/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BRAINTREE
    WEYMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $6,377,072.00
    State Cost: $1,594,268.00
    Total Cost: $7,971,340.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/24/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/03/2021
    Project Management
    25% Design 25% Package Received 05/14/2025
    75% Design 75% Package Received 05/14/2025