Project Description:
BOURNE- SANDWICH- RESURFACING AND RELATED WORK ON ROUTE 6
Location:
  • Town of Bourne
  • Town of Sandwich
  • Construction Begins: Spring 2025
    Resident Engineer: Gabriel Rodrigues
    Construction Bid Price: $7,642,386.00
    District: District 5
    Current Status: RT 6 WB complete. Contractor has shutdown until Spring 2027. Scheduled work hours are Monday through Friday, 9:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 09/23/2026)

    Contracts (1) Progress
    # 129789 -- Construction Contract
    Resurfacing and Related Work on Route 6 47% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/11/2025
    Contract Information
    Project Designer:
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    RT 6 WB complete. Contractor has shutdown until Spring 2027. Scheduled work hours are Monday through Friday, 9:00 PM to 5:00 AM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/24/2021
    Project Initiation Form PIF Approved 02/24/2021
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/26/2024
    Project Status Advertised 03/22/2025
    Project Management
    100% Design 100% Package Received 12/16/2024
    25% Design 25% Package Received 08/26/2024
    75% Design 75% Package Received 08/26/2024
    Final Design PS&E Received 12/16/2024
    Final Design PS&E Received - Resub 1 02/14/2025