| Project Description: |
BOURNE- SANDWICH- RESURFACING AND RELATED WORK ON ROUTE 6
|
| Location: |
|
| Construction Begins: | Spring 2025 |
| Resident Engineer: | Gabriel Rodrigues![]() |
| Construction Bid Price: | $7,642,386.00 |
| District: | District 5 |
| Current Status: | Contractor has acquired field office and submitted commencement submittals. Contractor has adjusted/rebuilt drainage structures, and tree trimming/clearing. Contractor has demobilized for the winter. Scheduled work hours are Sunday through Friday, 9:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 01/09/2026) |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||