BERNARDSTON- DECK REPLACEMENT, B-10-021 (0WV & 0WW), I-91 OVER RIVER STREET
This project will replace the deteriorated concrete decks on two bridges in Bernardston carrying I-91 over River Street.
Location:
  • Town of Bernardston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Gregory Mischel
    Estimated Total Contract Cost: $10,043,000.00
    Estimated Total Federal Participating Construction Cost: $10,499,500.00
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 115789 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2021
    Project Initiation Form PIF Entered 02/24/2021
    Project Initiation Form PRC Submitted 02/26/2021
    Project Review Committee PRC Approved 03/02/2021
    Project Management