ATTLEBORO- NORTH ATTLEBOROUGH- MANSFIELD- FOXBOROUGH- RESURFACING AND RELATED WORK ON I-95
Location:
  • City of Attleboro
  • Town of Mansfield
  • Town of North Attleborough
  • Construction Begins: Spring 2026
    Resident Engineer: Eric Borman
    Construction Bid Price: $14,384,585.94
    District: District 5
    Current Status: JHL: Crew not mobilized to site. NE Traffic: Started installation of Advanced Warning Signs. Normal work hours are Sunday through Friday, 9:00 PM to 5:00 AM. Scheduled work hours are Sunday through Friday, 9:00PM to 5:00AM. Expect periodic lane closures, detours, and restrictions. (as of 09/23/2026)

    Contracts (1) Progress
    # 133277 -- Construction Contract
    Resurfacing and Related Work on I-95

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    JHL: Crew not mobilized to site. NE Traffic: Started installation of Advanced Warning Signs. Normal work hours are Sunday through Friday, 9:00 PM to 5:00 AM. Scheduled work hours are Sunday through Friday, 9:00PM to 5:00AM. Expect periodic lane closures, detours, and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/24/2021
    Project Initiation Form PIF Approved 02/24/2021
    Project Initiation Form PRC Submitted 02/25/2021
    Project Review Committee PRC Approved 03/04/2021
    Project Status Advertised 12/27/2025
    Project Management
    100% Design 100% Package Received 10/06/2025
    100% Design 100% Package Comments to DE 10/21/2025
    25% Design 25% Package Received 07/25/2025
    25% Design 25% Package Received 07/25/2025
    75% Design 75% Package Received 07/25/2025
    75% Design 75% Package Comments to DE 08/26/2025
    Final Design PS&E Received 10/06/2025
    Final Design PS&E Received - Resub 1 12/09/2025