Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WAREHAM- RESURFACING AND RELATED WORK ON I-195
Location:
  • Town of Wareham
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $10,516,440.72
    Estimated Total Federal Participating Construction Cost: $10,358,338.93
    District: District 5
    Current Status: 75% Package Comments to DE (as of 03/20/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/24/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/24/2021
    Project Initiation Form PIF Approved 02/24/2021
    Project Initiation Form PRC Submitted 02/26/2021
    Project Review Committee PRC Approved 03/04/2021
    Project Management
    25% Design 25% Package Received 12/08/2022
    75% Design 75% Package Received 12/08/2022
    75% Design 75% Package Comments to DE 03/20/2023