Project Description:
LAWRENCE- BRIDGE REPLACEMENT, L-04-012, SHORT STREET OVER SPICKET RIVER
Location:
  • City of Lawrence
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $3,695,630.40
    Estimated Total Federal Participating Construction Cost: $3,969,380.80
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 12/21/2022 )

    Contracts (1) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: LAWRENCE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $3,167,683.00
    State Cost: $0.00
    Total Cost: $3,167,683.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2021
    Project Need Form PNF Approved 02/25/2021
    Project Initiation Form PIF Entered 02/25/2021
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/02/2021
    Project Management
    Consultant Contract Process NTP Issued 12/21/2022