Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SALEM- BRIDGE REPLACEMENT, S-01-024, JEFFERSON AVENUE OVER PARALLEL STREET
Location:
  • City of Salem
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2026
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $3,383,640.00
    Estimated Total Federal Participating Construction Cost: $3,634,280.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: SALEM
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $3,123,360 (HIP-BR)
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $2,498,688.00
    State Cost: $624,672.00
    Total Cost: $3,123,360.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2021
    Project Need Form PNF Approved 02/25/2021
    Project Initiation Form PIF Entered 02/25/2021
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/03/2021
    Project Management