Project Description: |
CHICOPEE- HUGH SCOTT STREIBER ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
The project proposes to install new sidewalks and replace existing sidewalks as well as improved crosswalks that will improve connectivity to Hugh Scott Streiber School from Irene Court and a portion of Irene Street, Streiber Drive (from Memorial Drive to the school), Telegraph Ave (from Prospect to the school), along Chicopee Housing Authority from Debra Drive to Strieber Drive, and along the front of the school.
|
Location: |
|
Design Responsibility: | Consultant |
Construction Begins: | Summer 2026 |
Project Manager: | Stephanie Upson |
Estimated Total Contract Cost: | $2,333,724.85 |
Estimated Total Federal Participating Construction Cost: | $2,511,115.95 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
District: | District 2 |
Current Status: | 25% Package Comments to DE (as of 11/18/2024 ) |
|