Project Description:
SPRINGFIELD- REBECCA M. JOHNSON ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
Intersection improvements to Dartmouth, Bay, Yale, & Catherinne Streets. Sidewalk improvement in proximity to school, and traffic calming on Catherine Street
Location:
  • City of Springfield
  • Construction Begins: Summer 2025
    Resident Engineer: Robert Wrzesinski
    Construction Bid Price: $982,491.25
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2

    Contracts (2) Progress
    # 130935 -- Construction Contract
    Rebecca M. Johnson Elementary School Improvements (SRTS)
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/10/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $672,931.20
    State Cost: $168,232.80
    Total Cost: $841,164.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2021
    Project Need Form PNF Approved 01/01/1900
    Project Initiation Form PIF Entered 02/25/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 03/16/2021
    Project Review Committee PRC Approved 03/16/2021
    Project Status Advertised 06/28/2025
    Project Management
    100% Design 100% Package Received 09/25/2024
    100% Design 100% Package Comments to DE 11/04/2024
    25% Design 25% Package Received 12/13/2023
    25% Design 25% Package Comments to DE 01/19/2024
    25% Design Design Public Hearing 06/11/2024
    75% Design 75% Package Received 09/25/2024
    Final Design PS&E Received 04/16/2025
    Final Design PS&E Received - Resub 1 05/28/2025