Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BARRE- BRIDGE REPLACEMENT, B-02-004, OLD COLDBROOK ROAD OVER PRINCE RIVER
The proposed project initially consisted of replacement of the superstructure. After the initial investigations, a full bridge replacement is now being considered. The project limits extend approximately 150 feet in either direction from the ends of the current bridge. Bicycle and pedestrian facilities do not exist within this area; however, accommodations are currently being considered in the design. Options are also being investigated on routes that may be necessary for a detour during construction.
Location:
  • Town of Barre
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Adam W Kiel
    Estimated Total Contract Cost: $6,878,750.40
    Estimated Total Federal Participating Construction Cost: $7,307,250.60
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 2
    Current Status: 25% Package Comments to DE (as of 10/21/2025 )

    Contracts (2) Progress
    # 115772 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 115778 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: BARRE
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $5,926,038, Design Status = Approved, YOE = 4%
  • Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $5,926,038.00
    State Cost: $0.00
    Total Cost: $5,926,038.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2021
    Project Need Form PNF Approved 01/01/1900
    Project Initiation Form PIF Entered 02/25/2021
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/02/2021
    Project Management
    25% Design 25% Package Received 08/15/2025
    25% Design 25% Package Comments to DE 10/21/2025
    Consultant Contract Process Scope to DE 07/27/2022
    Consultant Contract Process NTP Issued 04/12/2023