Project Description: |
BARRE- BRIDGE REPLACEMENT, B-02-004, OLD COLDBROOK ROAD OVER PRINCE RIVER
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Spring 2026 |
Project Manager: | Adam W Kiel |
Estimated Total Contract Cost: | $1,052,568.00 |
Estimated Total Federal Participating Construction Cost: | $1,196,100.00 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
District: | District 2 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 04/12/2023 ) |
|
Bridges
|
|
|
|