Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AUBURN- OXFORD- RESURFACING AND RELATED WORK ON I-290 AND I-395
Location:
  • Town of Auburn
  • Town of Oxford
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Kwabena Kantanka
    Construction Bid Price: $7,147,990.50
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3

    Contracts (1) Progress
    # 124912 -- Construction Contract
    Resurfacing and Related Work on I-290 and I-395

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/04/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: AUBURN
    OXFORD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $5,980,000, Design Status = Approved
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - Interstate Maintenance
    Federal Cost: $5,382,000.00
    State Cost: $598,000.00
    Total Cost: $5,980,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/25/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 02/26/2021
    Project Review Committee PRC Approved 03/04/2021
    Project Status Advertised 12/30/2023
    Project Management
    75% Design 75% Package Received 08/30/2023
    75% Design 75% Package Comments to DE 10/02/2023
    Final Design PS&E Received 11/06/2023
    Final Design PS&E Received - Resub 1 12/04/2023