Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
GILL- ERVING- RESURFACING AND RELATED WORK ON ROUTE 2
Location:
  • Town of Erving
  • Town of Gill
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Koby J Lemrise
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project