| Project Description: |
DUDLEY- SOUTHBRIDGE- RESURFACING AND RELATED WORK ON ROUTE 131
This project will resurface Route 131 in Southbridge and Dudley from mile-marker 5.6 to mile-marker
9.7. Maintenance repair of existing drainage systems safety systems traffic signage and multimodal accommodations may be included.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Winter 2026/2027 |
| Project Manager: | Koby J Lemrise![]() |
| Estimated Total Contract Cost: | $4,870,753.35 |
| Estimated Total Federal Participating Construction Cost: | $5,215,472.74 |
| Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
| District: | District 3 |
| Current Status: | 25% Package Comments to DE (as of 07/14/2025 ) |
|