Project Description:
UXBRIDGE- BRIDGE REPLACEMENT, U-02-051, HOMEWARD AVENUE OVER PROVIDENCE WORCESTER RAILROAD
Location:
  • Town of Uxbridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $3,818,888.34
    Estimated Total Federal Participating Construction Cost: $4,166,060.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: UXBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $4,499,345, Design Status = Approved, YOE = 8%
  • Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,599,476.00
    State Cost: $899,869.00
    Total Cost: $4,499,345.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2021
    Project Need Form PNF Approved 01/01/1900
    Project Initiation Form PIF Entered 02/25/2021
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/02/2021
    Project Management