Project Description:
RANDOLPH- CANTON- DEDHAM- MILTON- WESTWOOD- PAVEMENT AND BRIDGE PRESERVATION ON I-95 AND I-93
The work to be done under this Contract consists of: full width pavement micomilling and resurfacing with Ultra Thin Bonded Overlay (UTBO) on Route I-93/I-95 in the Towns of Westwood, Dedham, Canton and Milton. The roadway shall be micromilled 1 inch and paved with 1 inch of UTBO Polymer Modified -in order to prevent breaking through into the penetrated stone. However, consideration should also be given, to obtaining paving cores beneath decks and discuss increasing the milling depths in these locations, together with placement of new intermediate lift as a matter of course. Bridge approaches and departures will be reviewed and re-profiled as needed to improve rideability and to provide smooth transitions. The work also includes performance bridge repairs and maintenance work to the following bridges: I-95 NB/US1/ST128 over the Neponset River and I-95 NB/SB over I-95/US1/ST128 in Canton; I-95 NB/ST128 over AMTRAK/MBTA and I-95/ ST128 over University Ave in Dedham; Ponkapoag Trail over I-93/US1 in Milton; and, I-95 NB/I-95 SB /US1 SB over the MBTA/CSX and East Street over I-95/US1/ST 128 in Westwood.
Location:
  • Town of Canton
  • Town of Dedham
  • Town of Milton
  • Town of Randolph
  • Town of Westwood
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Eric I Nova
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • C02026 
    • C02027 
    • C02036 
    • D05047 
    • D05048 
    • M25028 
    • W31005 
    • W31013 
    • W31014 
    • W31015 
    See the Milestone Details tab for additional Project information
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CANTON
    DEDHAM
    WESTWOOD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Project description change and estimate decrease from 29,899,107.00 to $18.3m via STIP action 5.
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - Interstate Maintenance
    Federal Cost: $16,500,357.90
    State Cost: $1,833,373.10
    Total Cost: $18,333,731.00