Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WEST SPRINGFIELD- CHICOPEE- PAVEMENT AND BRIDGE PRESERVATION ON I-91
The work to be completed under this contract consists of roadway fine milling and pavement resurfacing on Interstate 91 mainline and ramps at interchanges 10A and 10B in the cities of Chicopee and West Springfield. The project begins in Chicopee at mile 8.518 and extends northerly into West Springfield ending at mile 10.504. The length of the project is 1.98 miles.
Location:
  • City of Chicopee
  • Town of West Springfield
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $9,118,238.15
    Estimated Total Federal Participating Construction Cost: $9,344,780.23
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 100% Package Received (as of 09/12/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: WEST SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - Interstate Maintenance
    Federal Cost: $5,391,360.00
    State Cost: $599,040.00
    Total Cost: $5,990,400.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/25/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 02/26/2021
    Project Review Committee PRC Approved 03/04/2021
    Project Review Committee Resubmitted 10/02/2024
    Project Management
    100% Design 100% Package Received 09/12/2024
    100% Design 100% Package Received 09/12/2024
    25% Design 25% Package Received 06/03/2024
    75% Design 75% Package Received 06/03/2024
    75% Design 75% Package Comments to DE 07/08/2024
    Final Design PS&E Received 09/12/2024