Project Description:
FALL RIVER- MARY FONSECA ELEMENTARY SCHOOL (SRTS)
Location:
  • City of Fall River
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2025
    Project Manager: Linda Walsh
    Estimated Total Contract Cost: $690,619.00
    Estimated Total Federal Participating Construction Cost: $811,990.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: FALL RIVER
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $727,543.20
    State Cost: $181,885.80
    Total Cost: $909,429.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/26/2021
    Project Need Form PNF Approved 02/17/2021
    Project Initiation Form PIF Entered 02/26/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 02/26/2021
    Project Review Committee PRC Approved 03/16/2021
    Project Management