SPRINGFIELD- CHICOPEE- INTERSTATE MAINTENANCE AND RELATED WORK ON I-91 AND I-391
The work to be completed under this contract consists of roadway fine milling, pavement resurfacing, and bridge preservation on Interstate I-91 and I-391 mainline and ramps in the cities of Chicopee and Springfield. The project begins in Springfield and extends northerly into Chicopee including work on I-391 The length of the project is 2.26 miles. The work includes bridge deck repairs, bridge joint repairs/replacement, bridge resurfacing, clearing roadway side slopes, removal of build-up material on shoulders to restore country drainage, adjusting and/or rebuilding drainage structures, repairing guardrail, installing recessed pavement markings and slotted pavement markers, implementing temporary traffic controls, installing erosion and sedimentation control measures, and other incidental items as set forth in the proposal and required to complete the work.
Location:
  • City of Chicopee
  • City of Springfield
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Matthew Coughlin
    Construction Bid Price: $27,976,663.00
    District: District 2

    Contracts (1) Progress
    # 124913 -- Construction Contract
    Interstate Maintenance and Related Work on I-91 and I-391 1% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 03/18/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/01/2021
    Project Initiation Form PIF Entered 03/01/2021
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/04/2021
    Project Status Advertised 12/30/2023
    Project Management
    100% Design 100% Package Received 04/14/2023
    25% Design 25% Package Received 09/06/2022
    75% Design 75% Package Received 09/06/2022
    75% Design 75% Package Comments to DE 11/01/2022
    Final Design PS&E Received 04/14/2023
    Final Design PS&E Received - Resub 1 06/29/2023
    Final Design PS&E Received - Resub 2 08/14/2023