Project Description:
FITCHBURG- ASHBY- RESURFACING AND RELATED WORK ON ROUTE 31
The project consists of resurfacing approximately 5.3 miles of State Route 31 from John Fitch Highway in Fitchburg to Turnpike Road in Ashby to prevent further deterioration and more extensive/expensive repairs long term. Resurfacing will take place within the existing edges of road and will include cleaning drainage structures, piping, inlets, and outlets within the State Highway Layout (SHLO).
Location:
  • Town of Ashby
  • City of Fitchburg
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Adam W Kiel
    Estimated Total Contract Cost: $8,866,388.38
    Estimated Total Federal Participating Construction Cost: $8,934,399.13
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: 75% Package Received (as of 03/20/2025 )

    Contracts (1) Progress
    # 115797 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: ASHBY
    FITCHBURG
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $4,657,876.00
    State Cost: $1,164,469.00
    Total Cost: $5,822,345.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/01/2021
    Project Initiation Form PIF Entered 03/01/2021
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/04/2021
    Project Management
    25% Design 25% Package Received 03/20/2025
    75% Design 75% Package Received 03/20/2025
    Consultant Contract Process Scope to DE 12/12/2022
    Consultant Contract Process NTP Issued 05/02/2023
    Consultant Contract Process Workhours Approved 04/14/2023