Project Description:
DISTRICT 5- TRAFFIC SIGNAL MASTER CONTROL AND CABINET ASSEMBLY INSTALLATION AT VARIOUS LOCATIONS
Location:
  • City of Taunton
  • Construction Begins: Winter 2021/2022
    Resident Engineer: David Todesco
    Construction Bid Price: $537,955.00
    District: District 5

    Contracts (1) Progress
    # 117003 -- Construction Contract
    Installation of Traffic Signal Control Cabinet Assemblies and Foundations at Various Locations Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/18/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/12/2021
    Project Need Form PNF Approved 01/01/1900
    Project Initiation Form PIF Entered 03/12/2021
    Project Initiation Form PRC Submitted 03/30/2021
    Project Review Committee PRC Approved 04/05/2021
    Project Status Advertised 12/18/2021
    Project Management
    100% Design 100% Package Received 06/15/2021
    Final Design PS&E Received 12/06/2021
    Final Design PS&E to FAPRO 12/08/2021