DISTRICT 5- SCHEDULED AND EMERGENCY STEEL BEAM REPAIRS AT VARIOUS LOCATIONS
Location:
Construction Begins: Autumn 2021
Resident Engineer: Scott Borges
Construction Bid Price: $946,117.90
District: District 5
Current Status: W.O. #9, Viaduct Bridge Nos. N-06-020 (3TY, 3U0), New Bedford: Steel Beam End Repairs @ I-195 over Route 18, Purchase, State and County Streets in New Bedford. Work Order is on-going with an anticipated completion in July 2024. NormalScheduled work hours are Monday thru Friday 6:30 AM to 2:30 AM. (as of 05/02/2024)
Additional Info: SPS crew continued the assembly of work platforms and preparations for beam end repairs at piers 7, 8 and 9. (as of 05/02/2024)

Contracts (1) Progress
# 116675 -- Construction Contract
DISTRICT 5: Scheduled and Emergency Steel Beam Repairs at Various Locations 59% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/16/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/16/2021
    Project Need Form PNF Approved 01/01/1900
    Project Initiation Form PIF Entered 03/16/2021
    Project Initiation Form PRC Submitted 03/17/2021
    Project Review Committee PRC Approved 03/22/2021
    Project Status Advertised 10/30/2021
    Project Management
    100% Design 100% Package Received 07/29/2021
    100% Design 100% Package Comments to DE 08/30/2021
    Final Design PS&E Received 09/10/2021
    Final Design PS&E to FAPRO 10/21/2021