Project Description: |
DISTRICT 5- SCHEDULED AND EMERGENCY STEEL BEAM REPAIRS AT VARIOUS LOCATIONS
|
Location: | |
Construction Begins: | Autumn 2021 |
Resident Engineer: | Scott Borges |
Construction Bid Price: | $946,117.90 |
District: | District 5 |
Current Status: | W.O. #9, Viaduct Bridge Nos. N-06-020 (3TY, 3U0), New Bedford: Steel Beam End Repairs @ I-195 over Route 18, Purchase, State and County Streets in New Bedford. Work Order is on-going with an anticipated completion in July 2024. NormalScheduled work hours are Monday thru Friday 6:30 AM to 2:30 AM. (as of 05/02/2024) |
Additional Info: | SPS crew continued the assembly of work platforms and preparations for beam end repairs at piers 7, 8 and 9. (as of 05/02/2024) |
|