SHREWSBURY- BRIDGE PRESERVATION, S-14-022 & S-14-023, I-290 OVER NORTH QUINSIGAMOND AVENUE AND WEST MAIN STREET
Location:
  • Town of Shrewsbury
  • Construction Begins: Autumn 2021
    Resident Engineer: Alexa Grajo
    Construction Bid Price: $1,895,780.00
    District: District 3

    Contracts (1) Progress
    # 116502 -- Construction Contract
    Bridge Repair and Related Work (Including Painting) Bridge Nos. S-14-022 & S-14-023 Interstate 290 over North Quinsigamond Avenue and West Main Street Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/08/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/31/2021
    Project Initiation Form PIF Entered 03/31/2021
    Project Initiation Form PRC Submitted 03/31/2021
    Project Review Committee PRC Approved 06/03/2021
    Project Status Advertised 10/09/2021
    Project Management
    100% Design 100% Package Received 08/03/2021
    100% Design 100% Package Comments to DE 09/02/2021
    Final Design PS&E Received 09/03/2021
    Final Design PS&E Received - Resub 1 09/16/2021