| Project Description: |
BERNARDSTON- BRIDGE REPLACEMENT, B-10-001, ROUTE 10 OVER FALL RIVER AND DECK REPLACEMENT, B-10-018, ROUTE 10 OVER I-91
The project will consist of the full replacement of the bridge carrying Route 10 over Fall River and the preservation of the bridge carrying Route 10 over I-91 in the town of Bernardston. Work includes pavement milling and overlay and improvements to bicycle and pedestrian accommodations on Route 10.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Summer 2026 |
| Project Manager: | Gregory Mischel![]() |
| Estimated Total Contract Cost: | $37,014,867.00 |
| Estimated Total Federal Participating Construction Cost: | $38,525,560.25 |
| Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Franklin Regional Council of Governments. |
| District: | District 2 |
| Current Status: | 100% Package Received (as of 11/04/2025 ) |
|