BERNARDSTON- BRIDGE REPLACEMENT, B-10-001, ROUTE 10 OVER FALL RIVER AND DECK REPLACEMENT, B-10-018, ROUTE 10 OVER I-91
The project will consist of the full replacement of the bridge carrying Route 10 over Fall River and the preservation of the bridge carrying Route 10 over I-91 in the town of Bernardston. Work includes pavement milling and overlay and improvements to bicycle and pedestrian accommodations on Route 10.
Location:
  • Town of Bernardston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2026
    Project Manager: Gregory Mischel
    Estimated Total Contract Cost: $37,065,619.50
    Estimated Total Federal Participating Construction Cost: $38,525,560.25
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 08/22/2026 )

    Contracts (2) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/28/2021
    Project Need Form PNF Approved 04/28/2021
    Project Initiation Form PIF Entered 04/28/2021
    Project Initiation Form PIF Approved 04/28/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Status Advertised 08/22/2026
    Project Management
    100% Design 100% Package Received 11/04/2025
    100% Design 100% Package Comments to DE 11/30/2025
    25% Design 25% Package Received 10/11/2023
    25% Design 25% Package Comments to DE 11/21/2023
    75% Design 75% Package Received 01/24/2025
    75% Design 75% Package Comments to DE 02/27/2025
    Final Design PS&E Received 05/22/2026
    Final Design PS&E Received - Resub 1 07/28/2026
    Consultant Contract Process NTP Issued 12/22/2022