BERNARDSTON- BRIDGE REPLACEMENT, B-10-001, ROUTE 10 OVER FALL RIVER AND DECK REPLACEMENT, B-10-018, ROUTE 10 OVER I-91
The project will consist of the full replacement of the bridge carrying Route 10 over Fall River and the preservation of the bridge carrying Route 10 over I-91 in the town of Bernardston. Work includes pavement milling and overlay and improvements to bicycle and pedestrian accommodations on Route 10.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2026 |
Project Manager: | Gregory Mischel |
Estimated Total Contract Cost: | $27,520,547.00 |
Estimated Total Federal Participating Construction Cost: | $29,039,008.00 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Franklin Regional Council of Governments. |
District: | District 2 |
Current Status: | 25% Package Comments to DE (as of 11/21/2023 ) |
|