| Project Description: |
BERNARDSTON- BRIDGE REPLACEMENT, B-10-001, ROUTE 10 OVER FALL RIVER AND DECK REPLACEMENT, B-10-018, ROUTE 10 OVER I-91
The project will consist of the full replacement of the bridge carrying Route 10 over Fall River and the preservation of the bridge carrying Route 10 over I-91 in the town of Bernardston. Work includes pavement milling and overlay and improvements to bicycle and pedestrian accommodations on Route 10.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Autumn 2026 |
| Project Manager: | Gregory Mischel![]() |
| Estimated Total Contract Cost: | $37,065,619.50 |
| Estimated Total Federal Participating Construction Cost: | $38,525,560.25 |
| District: | District 2 |
| Current Status: | This project has been advertised for construction bids. (as of 08/22/2026 ) |
|