Project Description:
BREWSTER- ORLEANS- BRIDGE PRESERVATION ALONG THE ROUTE 6 CORRIDOR
Location:
  • Town of Brewster
  • Town of Orleans
  • Construction Begins: Spring 2022
    Resident Engineer: Ian Bettencourt
    Construction Bid Price: $2,939,977.00
    District: District 5
    Current Status: The Contractor continues their painting operations at Route 6 over Route 6A in Orleans. Expect lane shifts and closures daily. Prime will be utilizing day shifts to paint the Route 6A bridge and night shifts to blast and prime the bridge located at Freemans Way over Route 6. Expect nightly closures from Exit 85 - 89 Route 6. Normal work hours are Sunday through Thursday, 8:00 PM to 5:30 AM. Expect periodic lane closures and restrictions. (as of 11/21/2022)

    Contracts (1) Progress
    # 117710 -- Construction Contract
    Bridge Repairs and Related Work (Including Painting) along a Section of Route 6 30% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 05/24/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/29/2021
    Project Need Form PNF Approved 04/28/2021
    Project Initiation Form PIF Entered 04/29/2021
    Project Initiation Form PIF Approved 04/28/2021
    Project Initiation Form PRC Submitted 04/29/2021
    Project Review Committee PRC Approved 05/04/2021
    Project Status Advertised 04/02/2022
    Project Management
    100% Design 100% Package Received 12/17/2021
    Final Design PS&E Received 02/22/2022
    Final Design PS&E Received - Resub 1 03/11/2022
    Final Design PS&E Received - Resub 2 03/22/2022