BREWSTER- ORLEANS- BRIDGE PRESERVATION ALONG THE ROUTE 6 CORRIDOR
Location:
  • Town of Brewster
  • Town of Orleans
  • Construction Begins: Spring 2022
    Resident Engineer: Ian Bettencourt
    Construction Bid Price: $2,939,977.00
    District: District 5
    Current Status: •Prime coatings has shut down for the winter. Will return when temperatures are within limits in the spring. Scheduled work hours are Monday through Friday, 7:00 AM to 4:00 PM. Expect periodic lane closures and restrictions. (as of 03/12/2024)

    Contracts (1) Progress
    # 117710 -- Construction Contract
    Bridge Repairs and Related Work (Including Painting) along a Section of Route 6 75% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 05/24/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    •Prime coatings has shut down for the winter. Will return when temperatures are within limits in the spring. Scheduled work hours are Monday through Friday, 7:00 AM to 4:00 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/29/2021
    Project Need Form PNF Approved 04/28/2021
    Project Initiation Form PIF Entered 04/29/2021
    Project Initiation Form PIF Approved 04/28/2021
    Project Initiation Form PRC Submitted 04/29/2021
    Project Review Committee PRC Approved 05/04/2021
    Project Status Advertised 04/02/2022
    Project Management
    100% Design 100% Package Received 12/17/2021
    Final Design PS&E Received 02/22/2022
    Final Design PS&E Received - Resub 1 03/11/2022
    Final Design PS&E Received - Resub 2 03/22/2022