Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SHARON- WALPOLE- BRIDGE PRESERVATION ALONG THE I-95 CORRIDOR
Furnishing various artisans, materials, supplies, equipment and engineering services to perform bridge substructure, joint and painting along the I-95 corridor (Sharon) in District Five
Location:
  • Town of Sharon
  • Town of Walpole
  • Construction Begins: Spring 2022
    Resident Engineer: Fedner Pierre
    Construction Bid Price: $5,693,581.00
    District: District 5
    Current Status: Bridge Repairs and Painting over I-95, High Plain St Rte. 27 Sharon/Walpole, Scheduled work hours are Monday through Sunday, 9:00 PM to 5:30AM. Expect periodic lane closures and restrictions, (as of 03/31/2025)

    Contracts (1) Progress
    # 117131 -- Construction Contract
    Bridge Repairs and Related Work (Including Painting) along a Section of Interstate 95 81% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 04/01/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge Repairs and Painting over I-95, High Plain St Rte. 27 Sharon/Walpole, Scheduled work hours are Monday through Sunday, 9:00 PM to 5:30AM. Expect periodic lane closures and restrictions,
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/29/2021
    Project Need Form PNF Approved 04/29/2021
    Project Initiation Form PIF Entered 04/29/2021
    Project Initiation Form PIF Approved 04/29/2021
    Project Initiation Form PRC Submitted 04/29/2021
    Project Review Committee PRC Approved 05/04/2021
    Project Status Advertised 01/08/2022
    Project Management
    100% Design 100% Package Received 09/27/2021
    100% Design 100% Package Comments to DE 11/03/2021
    Final Design PS&E Received 11/16/2021
    Final Design PS&E Received - Resub 1 12/15/2021