| Project Description: |
SHARON- WALPOLE- BRIDGE PRESERVATION ALONG THE I-95 CORRIDOR
Furnishing various artisans, materials, supplies, equipment and engineering services to perform bridge substructure, joint and painting along the I-95 corridor (Sharon) in District Five
|
| Location: |
|
| Construction Begins: | Spring 2022 |
| Resident Engineer: | Fedner Pierre![]() |
| Construction Bid Price: | $5,693,581.00 |
| District: | District 5 |
| Current Status: | Bridge Repairs and Painting over I-95, High Plain St Rte. 27 Sharon/Walpole Paint concrete protective coating on 95 NB under S. Walpole St Bridge 14 Scheduled work hours are Sunday through Friday, 9:00 PM to 5:30AM. Expect periodic lane closures and restrictions, (as of 10/20/2025) |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||