Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SHARON- WALPOLE- BRIDGE PRESERVATION ALONG THE I-95 CORRIDOR
Furnishing various artisans, materials, supplies, equipment and engineering services to perform bridge substructure, joint and painting along the I-95 corridor (Sharon) in District Five
Location:
  • Town of Sharon
  • Town of Walpole
  • Construction Begins: Spring 2022
    Resident Engineer: Fedner Pierre
    Construction Bid Price: $5,693,581.00
    District: District 5
    Current Status: Bridge repairs and painting, Bridge concrete protective coating Scheduled work hours are Monday through Sunday, 8:00 PM to 5:30AM. Expect periodic lane closures and restrictions, (as of 10/17/2024)

    Contracts (1) Progress
    # 117131 -- Construction Contract
    Bridge Repairs and Related Work (Including Painting) along a Section of Interstate 95 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/01/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge repairs and painting, Bridge concrete protective coating Scheduled work hours are Monday through Sunday, 8:00 PM to 5:30AM. Expect periodic lane closures and restrictions,
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/29/2021
    Project Need Form PNF Approved 04/29/2021
    Project Initiation Form PIF Entered 04/29/2021
    Project Initiation Form PIF Approved 04/29/2021
    Project Initiation Form PRC Submitted 04/29/2021
    Project Review Committee PRC Approved 05/04/2021
    Project Status Advertised 01/08/2022
    Project Management
    100% Design 100% Package Received 09/27/2021
    100% Design 100% Package Comments to DE 11/03/2021
    Final Design PS&E Received 11/16/2021
    Final Design PS&E Received - Resub 1 12/15/2021