Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MONTAGUE- BRIDGE REPLACEMENT, M-28-034, NORTH LEVERETT ROAD OVER SAWMILL RIVER
Location:
  • Town of Montague
  • Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Ryan P. Wilcox
    Estimated Total Contract Cost: $5,766,649.20
    Estimated Total Federal Participating Construction Cost: $6,193,808.40
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 04/12/2024 )

    Contracts (1) Progress
    # 60139 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support servives to support the Bridge Preservation/Betterment Program. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: MONTAGUE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $5,153,248.00
    State Cost: $1,288,312.00
    Total Cost: $6,441,560.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/29/2021
    Project Need Form PNF Approved 04/28/2021
    Project Initiation Form PIF Entered 04/29/2021
    Project Initiation Form PIF Approved 04/29/2021
    Project Initiation Form PRC Submitted 05/17/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Management
    Consultant Contract Process NTP Issued 04/12/2024