SPRINGFIELD- 3 BRIDGE REPLACEMENTS, S-24-017, ST. JAMES AVENUE OVER CSX, S-24-070, TAPLEY STREET OVER I-291 AND CSX, S-24-071, ST. JAMES AVENUE OVER I-291 (DESIGN-BUILD)
The proposed project consists of transportation improvements to the intersections of St. James Ave and Interstate 291 and the reconstruction of the Tapley Street bridge over Interstate 291. The proposed improvements include the reconstruction the Tapley Street bridge, the St. James Avenue bridge over I-291, and the intersection of St. James Avenue and Page Boulevard. The intersection of the St. James Avenue, Page Boulevard and I-291 will be reconstructed to a diverging diamond interchange with a roundabout at the intersection of St. James Avenue and Page Boulevard. Improvements include bridge reconstruction, roadway construction drainage modification, new crosswalks, pavement markings / signage, dedicated turn lanes for predominant movements, buffered bicycle lanes, shared use paths and sidewalks with pedestrian curb ramps that meet current standards throughout the project area.
Location:
  • City of Springfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Courtney Sulerud
    Estimated Total Contract Cost: $264,014,306.90
    Estimated Total Federal Participating Construction Cost: $277,342,160.85
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 25% Package Received - Resub 1 (as of 07/02/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $216,000,000.00
    State Cost: $54,000,000.00
    Total Cost: $270,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/29/2021
    Project Need Form PNF Approved 04/29/2021
    Project Initiation Form PIF Entered 04/29/2021
    Project Initiation Form PIF Approved 04/29/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Review Committee Resubmitted 12/16/2025
    Project Management
    25% Design 25% Package Received 02/18/2026
    25% Design 25% Package Received - Resub 1 07/02/2026
    Consultant Contract Process NTP Issued 10/04/2022