Project Description:
BELLINGHAM- BRIDGE REPLACEMENT, B-06-022, MAPLE STREET OVER I-495
The proposed project consists of the replacement of the bridge on Maple Street over Interstate 495. Bicycle accommodations consisting of a usable shoulder have been provided in accordance with applicable design guides. A widened sidewalk is proposed on the eastern side of the bridge. The construction of the bridge is planned in two stages.
Location:
  • Town of Bellingham
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2026
    Project Manager: Kristine Chestna
    Estimated Total Contract Cost: $11,180,008.85
    Estimated Total Federal Participating Construction Cost: $12,078,987.40
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: Design Public Hearing (as of 03/20/2025 )

    Contracts (1) Progress
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BELLINGHAM
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $11,416,549.60
    State Cost: $2,854,137.40
    Total Cost: $14,270,687.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/03/2021
    Project Need Form PNF Approved 04/28/2021
    Project Initiation Form PIF Entered 05/03/2021
    Project Initiation Form PIF Approved 05/03/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Management
    25% Design 25% Package Received 08/26/2024
    25% Design 25% Package Comments to DE 09/27/2024
    25% Design 25% Package Received - Resub 1 02/14/2025
    25% Design Design Public Hearing 03/20/2025
    Consultant Contract Process NTP Issued 06/22/2022