| Project Description: |
HUNTINGTON- BRIDGE REPLACEMENT, H-27-008, ST 112 WORTHINGTON ROAD OVER WATER POND BROOK
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Winter 2026/2027 |
| Project Manager: | Thomas H Currier![]() |
| Estimated Total Contract Cost: | $4,231,000.00 |
| Estimated Total Federal Participating Construction Cost: | $4,896,250.00 |
| Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
| District: | District 1 |
| Current Status: | 25% Package Received (as of 01/19/2024 ) |
|
Bridges
|
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||