Project Description:
LANESBOROUGH- BRIDGE SUPERSTRUCTURE REPLACEMENT, L-03-015, US 7 WILLIAMSTOWN ROAD OVER BRODIE MOUNTAIN BROOK
Due to the condition of the existing structure, at a minimum, we anticipate this bridge project will consist of the replacement of the existing bridge overpass (superstructure) structure constructed in 1961. If required by design, this project may require the replacement of the entire bridge structure at the same location. No pedestrian or bicycle accommodation improvements are currently anticipated, except for slightly increasing the shoulder widths.
Location:
  • Town of Lanesborough
  • Design Responsibility: Consultant
    Construction Begins: Spring 2027
    Project Manager: William F Brown
    Estimated Total Contract Cost: $1,855,558.80
    Estimated Total Federal Participating Construction Cost: $1,993,007.60
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 08/16/2023 )

    Contracts (1) Progress
    # 115772 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LANESBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $1,721,959.20
    State Cost: $430,489.80
    Total Cost: $2,152,449.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/04/2021
    Project Need Form PNF Approved 05/04/2021
    Project Initiation Form PIF Entered 05/04/2021
    Project Initiation Form PIF Approved 05/04/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Management
    Consultant Contract Process Scope to DE 12/02/2021
    Consultant Contract Process NTP Issued 08/16/2023