Project Description:
NATICK- BRIDGE REPLACEMENT, N-03-010, SPEEN STREET OVER RR MBTA/CSX
Location:
  • Town of Natick
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Kristine Chestna
    Estimated Total Contract Cost: $6,182,976.80
    Estimated Total Federal Participating Construction Cost: $6,464,021.20
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NATICK
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $5,369,303.20
    State Cost: $1,342,325.80
    Total Cost: $6,711,629.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/04/2021
    Project Need Form PNF Approved 05/04/2021
    Project Initiation Form PIF Entered 05/04/2021
    Project Initiation Form PIF Approved 05/04/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021