REVERE- BRIDGE REPLACEMENT, R-05-015, REVERE BEACH PARKWAY OVER BROADWAY
This project involves the replacement of the bridge carrying Revere Beach Parkway over Broadway in Revere. The project begins along Broadway at the intersection of Revere Beach Parkway Eastbound ramps and Broadway and extends to the intersection of Revere Beach Parkway westbound ramps and Broadway to the north. The project limits along the Revere Beach Parkway corridor extend from the westbound on-ramp to the westbound off-ramp. Along with the bridge structure, the project includes roadway improvements on Broadway below the bridge from the Revere/Chelsea city line in the south to the intersection of Broadway with Taft Street/Page Street in the north. This will also include intersection improvements where the Revere Beach Parkway on and off ramps meet Broadway. In addition to the bridge replacement, this project will bring Revere Beach Parkway and Broadway up to current standards for safety as well as improving pedestrian and bicycle accommodations.
Location:
  • City of Revere
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Kristine Chestna
    Estimated Total Contract Cost: $14,637,228.54
    Estimated Total Federal Participating Construction Cost: $15,592,504.56
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 25% Package Received - Resub 2 (as of 02/26/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: REVERE
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $16,218,396.00
    State Cost: $4,054,599.00
    Total Cost: $20,272,995.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/06/2021
    Project Need Form PNF Approved 05/06/2021
    Project Initiation Form PIF Entered 05/06/2021
    Project Initiation Form PIF Approved 05/06/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Management
    25% Design 25% Package Received 07/08/2024
    25% Design 25% Package Comments to DE 08/07/2024
    25% Design 25% Package Received - Resub 1 11/05/2024
    25% Design 25% Package Received - Resub 2 02/26/2025
    25% Design Design Public Hearing 01/15/2025
    Consultant Contract Process NTP Issued 12/08/2021