| Project Description: |
CHICOPEE- BRIDGE REPLACEMENT, C-13-038, I-391 OVER (ST 116) CHICOPEE STREET
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Summer 2026 |
| Project Manager: | Aleksey N Belov![]() |
| Estimated Total Contract Cost: | $167,223,681.90 |
| Estimated Total Federal Participating Construction Cost: | $172,682,660.85 |
| Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
| District: | District 2 |
| Current Status: | Design Public Hearing (as of 12/15/2025 ) |
|
Bridges
|
||||||
|
|
||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||