Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHICOPEE- BRIDGE REPLACEMENT, C-13-038, I-391 OVER (ST 116) CHICOPEE STREET
Location:
  • City of Chicopee
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Aleksey N Belov
    Estimated Total Contract Cost: $167,389,411.00
    Estimated Total Federal Participating Construction Cost: $172,621,430.61
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 05/02/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/06/2021
    Project Need Form PNF Approved 05/06/2021
    Project Initiation Form PIF Entered 05/06/2021
    Project Initiation Form PIF Approved 05/06/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Status Advertised 05/02/2026
    Project Management
    100% Design 100% Package Received 04/17/2026
    25% Design 25% Package Received 06/25/2025
    25% Design 25% Package Received - Resub 1 11/07/2025
    25% Design 25% Package Received - Resub 2 03/25/2026
    25% Design Design Public Hearing 12/15/2025
    Final Design PS&E to FAPRO 04/17/2026
    Final Design PS&E to FAPRO 04/20/2026
    Consultant Contract Process NTP Issued 12/09/2022