Project Description:
HOLDEN- BRIDGE REPLACEMENT, H-18-004, SALISBURY STREET OVER G&W RAILROAD
The purpose of this project is to replace the bridge carrying Salisbury Street over the Providence and Worcester Railroad. The project will also include roadway pavement overlay, new pavement markings, as well as bicycle and ADA compliant pedestrian curb ramps and sidewalks. A 10-foot shared use path tapers to a 5.5-foot-wide sidewalk at the bridge on the west side in accordance with all applicable design guides. A detour is being proposed during the summer months when school is out to replace the bridge.
Location:
  • Town of Holden
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Stephen Soma
    Estimated Total Contract Cost: $6,346,058.70
    Estimated Total Federal Participating Construction Cost: $6,897,435.73
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: Design Public Hearing (as of 02/20/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: HOLDEN
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $7,420,917, Design Status = 25%
  • Category FA - Next Generation Bridge GANs
    Federal Cost: $6,174,203.20
    State Cost: $1,543,550.80
    Total Cost: $7,717,754.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/07/2021
    Project Need Form PNF Approved 05/07/2021
    Project Initiation Form PIF Entered 05/07/2021
    Project Initiation Form PIF Approved 05/07/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Management
    25% Design 25% Package Received 06/03/2024
    25% Design Design Public Hearing 07/20/2023
    25% Design Design Public Hearing 02/20/2025
    Consultant Contract Process Scope to DE 02/07/2023
    Consultant Contract Process NTP Issued 03/20/2023