Project Description:
WORCESTER- SUPERSTRUCTURE REPLACEMENT, W-44-091, I-290 OVER EAST CENTRAL STREET
The proposed project consists of the superstructure replacement of the bridge carrying I-290 over East Central Street. Once the project has been completed, the life cycle and serviceability of the bridge will be extended and safety for all roadway users will be increased. The proposed work along Interstate-290 is designed to match the existing geometry of the freeway both horizontally and vertically without creating a larger footprint. Existing 16-foot median with 2-foot left shoulders is being removed and replaced with a two-sided F-Shape barrier, resulting in new 6-foot left shoulders with 2-foot horizontal buffers to the median barrier.
Location:
  • City of Worcester
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2026
    Project Manager: Jacob Tanoglu
    Estimated Total Contract Cost: $34,724,831.94
    Estimated Total Federal Participating Construction Cost: $35,738,186.81
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: 75% Package Received (as of 09/25/2025 )

    Contracts (1) Progress
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Project AC'd between 2026 & 2027, Total Project Cost = $30,929,761, Design Status = 25%
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $9,083,360.00
    State Cost: $2,270,840.00
    Total Cost: $11,354,200.00

    Planned Federal FY: 2027
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Project AC'd between 2026 & 2027, Total Project Cost = $30,929,761, Design Status = 25%
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $15,660,448.80
    State Cost: $3,915,112.20
    Total Cost: $19,575,561.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/10/2021
    Project Need Form PNF Approved 05/03/2021
    Project Initiation Form PIF Entered 05/10/2021
    Project Initiation Form PIF Approved 05/10/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Management
    25% Design 25% Package Received 08/30/2024
    25% Design 25% Package Comments to DE 11/22/2024
    25% Design Design Public Hearing 04/24/2025
    75% Design 75% Package Received 09/25/2025
    Consultant Contract Process Scope to DE 09/14/2021
    Consultant Contract Process Workhours Approved 08/05/2022