AMESBURY- HAVERHILL- LOWELL- METHUEN- BRIDGE PRESERVATION BUNDLE ALONG I-495
Location:
  • Town of Amesbury
  • City of Haverhill
  • City of Lowell
  • Town of Methuen
  • Construction Begins: Summer 2022
    Resident Engineer: John Mitchell
    Construction Bid Price: $5,895,055.15
    District: District 4

    Contracts (1) Progress
    # 117900 -- Construction Contract
    Structural Repairs and Related Work to Six (6) Bridges along a Section of Interstate 495 80% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 07/07/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/11/2021
    Project Initiation Form PIF Entered 05/11/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 05/13/2021
    Project Status Advertised 04/30/2022
    Project Management
    100% Design 100% Package Received 12/08/2021
    100% Design 100% Package Comments to DE 01/21/2022
    Final Design PS&E Received 02/10/2022
    Final Design PS&E Received - Resub 1 03/10/2022