Project Description:
AMESBURY- HAVERHILL- LOWELL- METHUEN- BRIDGE PRESERVATION BUNDLE ALONG I-495
Location:
  • Town of Amesbury
  • City of Haverhill
  • City of Lowell
  • Town of Methuen
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2022
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $7,592,652.60
    Estimated Total Federal Participating Construction Cost: $7,845,545.90
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the STATEWIDE.
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 04/30/2022 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: HAVERHILL
    LOWELL
    NORTH ANDOVER
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $6,252,852.80
    State Cost: $1,563,213.20
    Total Cost: $7,816,066.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/11/2021
    Project Initiation Form PIF Entered 05/11/2021
    Project Initiation Form PRC Submitted 05/11/2021
    Project Review Committee PRC Approved 05/13/2021
    Project Status Advertised 04/30/2022
    Project Management
    100% Design 100% Package Received 12/08/2021
    100% Design 100% Package Comments to DE 01/21/2022
    Final Design PS&E Received 02/10/2022
    Final Design PS&E Received - Resub 1 03/10/2022