NORTH ATTLEBORO- BRIDGE PAINTING AND REPAIRS ALONG I-295
Beam end repairs and clean (full removal) and paint.
Location:
  • Town of North Attleborough
  • Construction Begins: Summer 2022
    Resident Engineer: Eric Borman
    Construction Bid Price: $1,933,175.00
    District: District 5
    Current Status: No operations onsite October 2023, Contractor scheduled to remobilize November 1, 2023 Scheduled work hours are Monday through Friday 7:00 AM to 5:30 PM. Expect periodic lane closures and restrictions. Roadway closed to traffic. Detour in place. (as of 10/16/2023)
    Additional Info: Traffic control will consist of 2 11-foot lanes with Police details to assist motorists within work zone (as of 10/16/2023)

    Contracts (1) Progress
    # 118958 -- Construction Contract
    Cleaning, Painting and Structural Repairs to Two (2) Bridges (Nos. N-16-050 and N-16-053) on a Section of I-295

    Bridges

    Contract Dates
    Notice to Proceed: 09/02/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/13/2021
    Project Need Form PNF Approved 05/13/2021
    Project Initiation Form PIF Entered 05/13/2021
    Project Initiation Form PIF Approved 05/13/2021
    Project Initiation Form PRC Submitted 05/13/2021
    Project Review Committee PRC Approved 05/20/2021
    Project Status Advertised 07/09/2022
    Project Management
    100% Design 100% Package Received 08/23/2021
    100% Design 100% Package Comments to DE 09/17/2021
    Final Design PS&E Received 10/04/2021
    Final Design PS&E to FAPRO 06/27/2022