Project Description:
DISTRICT 5- VEGETATION REMOVAL AT VARIOUS LOCATIONS
The work consists of mechanically removing highway vegetation overgrowth on state highways in District 5 as directed by the Engineer. The work includes cutting grass and or weeds along under guardrail barriers and curbs. Work also includes the removal of small trees and brush from within the State Highway Limits by a vegetation removal crew and through use of an over the guardrail mower.
Location:
Construction Begins: Winter 2021/2022
Resident Engineer: Joseph Goncalves
Construction Bid Price: $978,110.00
District: District 5

Contracts (1) Progress
# 117127 -- Construction Contract
Vegetation Management (Mechanical) at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/04/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/13/2021
    Project Need Form PNF Approved 05/13/2021
    Project Initiation Form PIF Entered 05/13/2021
    Project Initiation Form PIF Approved 05/13/2021
    Project Initiation Form PRC Submitted 05/21/2021
    Project Review Committee PRC Approved 05/24/2021
    Project Status Advertised 01/08/2022
    Project Management
    100% Design 100% Package Received 10/01/2021
    Final Design PS&E Received 12/02/2021
    Final Design PS&E to FAPRO 12/03/2021