Project 612202
(Click here for a glossary of terms)
Project Description:
DISTRICT 5- VEGETATION REMOVAL AT VARIOUS LOCATIONS
Location:
Construction Begins:
Winter 2021/2022
Resident Engineer:
Joseph Goncalves
Construction Bid Price:
$978,110.00
District:
District 5
Contracts
(1)
Progress
# 117127 -- Construction Contract
Vegetation Management (Mechanical) at Various Locations
Completed
Bridges
- none -
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Contract Dates
Notice to Proceed:
03/04/2022
Contract Information
Project Designer:
In-House Boston
Funding Source:
Non Federal Aid
Construction Progress
Milestone Details
TIP/Funding
Project Issues
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
Construction Progress
Milestone Details
TIP/Funding
Project Issues
TIP Lines for
2024 - 2028
No TIP Data Available For This Project
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Project Task Information
Project Status
Project Need Form
PNF Entered
05/13/2021
Project Need Form
PNF Approved
05/13/2021
Project Initiation Form
PIF Entered
05/13/2021
Project Initiation Form
PIF Approved
05/13/2021
Project Initiation Form
PRC Submitted
05/21/2021
Project Review Committee
PRC Approved
05/24/2021
Project Status
Advertised
01/08/2022
Project Management
100% Design
100% Package Received
10/01/2021
Final Design
PS&E Received
12/02/2021
Final Design
PS&E to FAPRO
12/03/2021