Project Description:
DISTRICT 5- SCHDULED AND EMERGENCY PAVEMENT REPAIRS AND IMPROVEMENTS AT VARIOUS LOCATIONS IN AREA D (BARNSTABLE COUNTY)
Location:
Construction Begins: Summer 2022
Resident Engineer: Anthony Geller
Construction Bid Price: $1,837,685.00
District: District 5

Contracts (1) Progress
# 118828 -- Construction Contract
Scheduled and Emergency Pavement Repairs and Improvements at Various Locations in Area D Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/17/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/13/2021
    Project Need Form PNF Approved 05/13/2021
    Project Initiation Form PIF Entered 05/13/2021
    Project Initiation Form PIF Approved 05/13/2021
    Project Initiation Form PRC Submitted 05/21/2021
    Project Review Committee PRC Approved 05/24/2021
    Project Status Advertised 07/02/2022
    Project Management
    100% Design 100% Package Received 10/29/2021
    Final Design PS&E Received 01/18/2022
    Final Design PS&E to FAPRO 06/27/2022