Report by:
City
|
MassHighway District
|
MPO
|
State Senate
|
State Representative
|
US Congress
Enter a City or Road name to search for a new project:
search
Advanced Project Search
Project 612233
(Click here for a glossary of terms)
Project Description:
DISTRICT 4- VEGETATION MANAGAMENT (MECHANICAL) AT VARIOUS LOCATIONS
Location:
Construction Begins:
Spring 2022
Resident Engineer:
Scott Venuti
Construction Bid Price:
$428,600.96
District:
District 4
Contracts
(1)
Progress
# 117334 -- Construction Contract
Vegetation Management (Mechanical) at Various Locations
Completed
Bridges
- none -
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Contract Dates
Notice to Proceed:
03/29/2022
Contract Information
Project Designer:
In-House Boston
Funding Source:
Non Federal Aid
Construction Progress
Milestone Details
TIP/Funding
Project Issues
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
Construction Progress
Milestone Details
TIP/Funding
Project Issues
TIP Lines for
2026 - 2030
No TIP Data Available For This Project
Construction Progress
Milestone Details
TIP/Funding
Project Issues
Project Task Information
Project Status
Project Need Form
PNF Entered
05/21/2021
Project Initiation Form
PIF Entered
05/21/2021
Project Initiation Form
PRC Submitted
05/21/2021
Project Review Committee
PRC Approved
05/24/2021
Project Status
Advertised
02/05/2022
Project Management
100% Design
100% Package Received
11/29/2021
Final Design
PS&E Received
12/21/2021
Final Design
PS&E to FAPRO
01/06/2022