Project Description:
DISTRICT 3- SCHEDULED AND EMERGENCY FABRICATION AND INSTALLATION OF OVERHEAD AND GROUND MOUNTED GUIDE SIGNS AT VARIOUS LOCATIONS
This District-wide project will maintain and upgrade traffic and guide signage on State Highways in District 3.
Location:
Construction Begins: Spring 2022
Resident Engineer: Linda Terry
Construction Bid Price: $561,223.50
District: District 3

Contracts (1) Progress
# 117840 -- Construction Contract
Scheduled and Emergency Fabrication and Installation of Overhead and Ground Mounted Guide Signs at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/16/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/02/2021
    Project Initiation Form PIF Entered 06/14/2021
    Project Initiation Form PRC Submitted 06/14/2021
    Project Review Committee PRC Approved 06/15/2021
    Project Status Advertised 04/23/2022
    Project Management
    Final Design PS&E Received 04/01/2022
    Final Design PS&E to FAPRO 04/11/2022