BROCKTON- INTERSECTION IMPROVEMENTS AT ROUTE 123 (BELMONT STREET), PEARL STREET AND STONEHILL STREET
The project consist of a functional overlay, traffic signal reconstruction including the addition of left turn lanes on Pearl Street and Transit Priority Operation, and the upgrade to the bicycle and pedestrian accommodations.
Location:
  • City of Brockton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2028
    Project Manager: Alolade O Campbell
    Estimated Total Contract Cost: $7,069,500.00
    Estimated Total Federal Participating Construction Cost: $7,465,375.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (2) Progress
    # 115759 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: BROCKTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction; Total Cost is $7,465,375; TEC Score 60.61; Status is pre-25% Design. As of April 2023, not enough design information to quantify GHG Analysis
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $6,927,868.00
    State Cost: $1,731,967.00
    Total Cost: $8,659,835.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/03/2021
    Project Need Form PNF Approved 06/01/2021
    Project Initiation Form PIF Entered 06/03/2021
    Project Initiation Form PIF Approved 06/02/2021
    Project Initiation Form PRC Submitted 06/03/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Management