Project Description:
NEW BEDFORD- BICYCLE AND PEDESTRIAN RAMP CONSTRUCTION, ROUTE 6 (WB) TO MACARTHUR DRIVE
The project consists of the construction of a new bicycle, pedestrian ramp, and shared use path to allow access from Route 6 Westbound to MacArthur Drive.
Location:
  • City of New Bedford
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Adetoyin Ayoola Olaoye
    Estimated Total Contract Cost: $6,416,981.30
    Estimated Total Federal Participating Construction Cost: $6,819,355.10
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Received - Resub 3 (as of 10/02/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: NEW BEDFORD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,868,336.80
    State Cost: $467,084.20
    Total Cost: $2,335,421.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/03/2021
    Project Need Form PNF Approved 06/01/2021
    Project Initiation Form PIF Entered 06/03/2021
    Project Initiation Form PIF Approved 06/02/2021
    Project Initiation Form PRC Submitted 06/03/2021
    Project Review Committee PRC Approved 06/24/2021
    Project Management
    25% Design 25% Package Received 07/29/2022
    25% Design 25% Package Comments to DE 09/27/2023
    25% Design 25% Package Received - Resub 1 11/17/2023
    25% Design 25% Package Received - Resub 2 05/15/2024
    25% Design 25% Package Received - Resub 3 10/02/2024