BOSTON- LEAK SEALING, FIREPROOFING AND MISCELLANEOUS REPAIRS
Location:
Construction Begins: Autumn 2022
Resident Engineer: Nicholas Renaud
Construction Bid Price: $15,343,725.00
District: District 6

Contracts (2) Progress
# 115773 -- Design -- Services
Statewide - Master Service Agreement for design and review services. Final
# 120081 -- Construction Contract
Tunnel System Leak Sealing, Fireproofing and Miscellaneous Repairs (Including Painting) along Interstates 90 & 93 (Ted Williams and Thomas P. O’Neill Tunnels) and Route 1A (Su 24% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/29/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/26/2021
    Project Need Form PNF Approved 08/25/2021
    Project Initiation Form PIF Entered 08/26/2021
    Project Initiation Form PIF Approved 08/25/2021
    Project Initiation Form PRC Submitted 09/29/2021
    Project Review Committee PRC Approved 10/21/2021
    Project Status Advertised 08/27/2022
    Project Management
    75% Design 75% Package Received 07/02/2021
    75% Design 75% Package Comments to DE 11/30/2021
    Final Design PS&E Received 07/14/2022
    Final Design PS&E to FAPRO 08/23/2022