Project Description: |
SPRINGFIELD- BRIDGE REPLACEMENT, S-24-070, TAPLEY STREET OVER I-291 AND CSX
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2025 |
Project Manager: | Courtney Sulerud![]() |
Estimated Total Contract Cost: | $17,285,562.00 |
Estimated Total Federal Participating Construction Cost: | $17,925,768.00 |
District: | District 2 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|