Project Description: |
RUSSELL- BRIDGE REPLACEMENT, R-13-02T, BRIDGE STREET OVER WESTFIELD RIVER
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Summer 2028 |
Project Manager: | Caitlin A Marshall |
Estimated Total Contract Cost: | $22,699,845.00 |
Estimated Total Federal Participating Construction Cost: | $23,540,580.00 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
District: | District 1 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 11/02/2022 ) |
|
Bridges
|
|
|
|