Project Description:
PITTSFIELD- BRIDGE REPLACEMENT, P-10-003 & P-10-032, SOUTH STREET OVER HOUSATONIC RR & HOUSATONIC RIVER
Location:
  • City of Pittsfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $20,823,257.22
    Estimated Total Federal Participating Construction Cost: $22,412,151.98
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 75% Package Received (as of 05/18/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: PITTSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Moved from FFY 2026 to FFY 2027.
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $22,259,783.20
    State Cost: $5,564,945.80
    Total Cost: $27,824,729.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/16/2021
    Project Initiation Form PIF Entered 10/01/2021
    Project Initiation Form PRC Submitted 10/18/2021
    Project Review Committee PRC Approved 10/21/2021
    Project Management
    25% Design 25% Package Received 12/13/2024
    25% Design 25% Package Comments to DE 01/15/2025
    25% Design Design Public Hearing 06/12/2025
    75% Design 75% Package Received 05/18/2026