Project Description: |
NORTHAMPTON- BRIDGE REPLACEMENT, N-19-045, MAIN STREET LEEDS OVER MILL RIVER & N-19-046, MAIN STREET LEEDS OVER NORTH & SOUTH CHANNELS OF THE MILL RIVER
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Project Manager: | Ryan P. Wilcox |
Estimated Total Contract Cost: | $3,526,173.00 |
Estimated Total Federal Participating Construction Cost: | $3,787,371.00 |
District: | District 2 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 10/04/2023 ) |
|
Bridges
|
|
|
|