Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HATFIELD- WHATELY- BRIDGE PRESERVATION, H-11-030, W-33-019, W-33-020, ROUTES 5 & 10 OVER I-91 (SEPARATE CROSSINGS)
Location:
  • Town of Hatfield
  • Town of Whately
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Anthony Christakis
    Estimated Total Contract Cost: $33,124,168.18
    Estimated Total Federal Participating Construction Cost: $34,297,032.52
    District: District 2
    Current Status: 25% Package Received (as of 07/01/2024 )

    Contracts (1) Progress
    # 115749 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/16/2021
    Project Initiation Form PIF Entered 10/01/2021
    Project Initiation Form PRC Submitted 10/18/2021
    Project Review Committee PRC Approved 10/21/2021
    Project Management
    25% Design 25% Package Received 07/01/2024